A. When the PCD zone is assigned as an exclusive zone, the following shall apply:

1. The applicant shall commence construction no later than three years from the effective date of the zoning change. If, within such period, the construction specified in the approved preliminary development plan has not been commenced, the planning director shall notify the planning commission of same and the commission shall consider whether changed circumstances justify a zone change to rescind the PCD zone or if additional time is necessary to be conditioned in order to commence construction of the project. Initiation of a zone change to rescind the PCD zone, or to change any conditions of approval including those extending time periods, shall be subject to the provisions of Section 17.64.070 of this code.

2. With the exception of satellite pads, if a certificate of occupancy has not been issued for a substantial portion of the commercial structures in the first phase of a PCD zone within five years of the effective date of the PCD zone as determined by the planning director, he/she shall notify the planning commission of same and the commission shall consider whether changed circumstances justify a zone change to rescind the PCD zone or if additional time is necessary to be conditioned for the project to be completed. Initiation of a zone change to rescind the PCD zone, or to change any conditions of approval including those extending time periods, shall be subject to the provisions of Section 17.64.070 of this code.

3. With the exception of satellite pads, where the first phase is substantially developed and the remaining phases are undeveloped or in various stages of development and five years have lapsed since the effective date of the PCD zone as determined by the planning director, he/she shall notify the planning commission of same and the commission shall consider whether changed circumstances justify a zone change to rescind the PCD zone for the area containing the uncompleted phases or if additional time is necessary to be conditioned for the project to be completed. Initiation of a zone change to rescind the PCD zone, or to change any conditions of approval including those extending time periods, shall be subject to the provisions of Section 17.64.070 of this code.

B. When the PCD zone is used as a combining zone, no status review or other notification shall be required. Approved preliminary plans shall be subject to the same time periods as an approved site plan (Section 17.08.080D). If more than one preliminary development plan is approved for a site, the most recent approval shall supersede all previously approved plans. (Ord. 4009 § 2, 2001; Ord. 3656 § 2, 1995)