A. Grading shall be performed in accordance with the approved grading plan and the preliminary soils report and compaction tests shall be submitted to the city’s building director for each lot in a subdivision prior to recordation of the final map, except as the building director may determine that no public interest would be served thereby.

B. When any soils investigation has indicated any soil problems and a civil engineer has recommended the corrective action which is likely to prevent structural damage to each structure proposed to be constructed in the area where the soils problems exist, the final map or parcel map may be approved for recording subject to the following condition: The building director shall not approve any building permit on any lot within any new subdivision until a final soils report has been submitted to him showing that all corrective action set forth in the preliminary soils report and report of the soils investigation has been completed and until the civil engineer has certified that all corrective action likely to prevent any structural damage to any structure proposed to be constructed in the area where the soils problems exist, has been taken and completed to his satisfaction. (Ord. 3515 § 1, 1993)